The Australian government is pushing for a major expansion of hydropower as part of its Powering Australia Plan, which aims for 82 per cent renewable electricity by 2030. To meet these targets, officials plan to retire coal and gas plants while relying on wind and solar. Because these renewable sources are intermittent, the grid needs long-duration storage to remain stable. The Australian Energy Market Operator predicts demand for storage will rise sharply in the coming decades.
Massive Capacity on Paper
Australia currently operates around 8.5 GW of traditional and pumped hydro across more than 120 stations. These facilities provide between 5 per cent and 7 per cent of the nation’s power. Despite this, the country has a theoretical capacity of over 124 GW identified at potential sites. In February, the International Hydropower Association and its Australian members released a roadmap to accelerate these projects as part of the green transition.
According to the Australian Energy Market Operator’s draft 2026 Integrated System Plan, the country will need to develop 27 GW of storage by 2030. This figure is expected to climb to 55 GW by 2050. The president of the IHA, Malcolm Turnbull, said the technology is ready but needs policy support. “Let me be clear, if we want a successful clean energy transition and affordable electricity for Australians, we’re going to need more pumped storage,” Turnbull stated. He added that the project is essential and not optional.
Costs Escalating on the Ground
The proposed Snowy 2.0 expansion would add pumped hydro capacity to the Snowy Mountains Hydro-electric Scheme in New South Wales, Victoria, and South Australia. The system uses tunnels to move water between reservoirs, allowing the grid to store excess energy and release it during peaks. The goal is to create a massive battery that can operate for hours when solar and wind output drops. While the technology is proven, the financial reality has been difficult.
Originally estimated at $2 billion, the project cost has soared. A 2017 feasibility study suggested a cost of $5.4 billion to $6.9 billion. The government approved a $6.1 billion investment in 2018 before geological studies were finished or environmental permits were granted. This lack of preparation has likely contributed to the ballooning expenses.
Delays and Disputes
Progress has been slow since the project was approved in 2020. One of the three tunnel-boring machines became stuck just 150 metres into a 15-kilometre excavation due to unexpected soft ground. The machine was immobilized for nearly a year and then encountered further delays. In 2023, tunnel workers went on strike over pay and working conditions. These setbacks have pushed the projected cost past the $12 billion mark by 2023.
Despite the financial strain, the project is intended to provide a steady supply to a region that depends heavily on renewables. By storing water at high elevations and releasing it on demand, Snowy 2.0 would help stabilize the grid. The project demonstrates that large-scale storage is technically viable, but the economic and logistical hurdles remain significant. The expansion would increase the Snowy scheme by around 50 per cent by linking two reservoirs via tunnels to establish a pumped hydro project.